Friday 29 March 2013

Bunker renovations are finished on time

This week the Greenstaff managed to finish the bunker project that was started in March. The aim was to 'freshen' the bunkers up before the season starts. All 67 bunkers have had work done to them. Some have been drained such as the 3rd (below) and others have had the compacted layer taken out and replaced with fresh sand.

3rd Bunker Before
3rd Bunker After Drainage Added

It has taken a huge amount of effort from the Greenstaff. In total 354 labour hours were used and 110tonnes of sand moved. It will take some time for the bunkers to bed down, but we think it will be worth it. Just remember when you go in there that bunkers, are hazards!