Friday 28 March 2014

Spring Drainage Works at EGC

The last two weeks have been very intense at EGC. Last week all the greens,tees,approaches and collars were given their spring renovations. The main focus of the week was aeration and sanding with the greens receiving 40tonnes on their own. This week the intensity went up another level and 380 metres of drainage was installed in to the 15th fairway and snagging areas on the 1st,8th and 11th holes. This is part of our overall drainage programme which is into its second year now. With this work completed we now have 13 fairways and approaches which we consider 'acceptable' in extreme weather. Work is planned to the second fairway in the autumn and in year 4 all fairways should be up to standard.

The pictures below give you an idea of the work which took place. We did 850metres over the week and with the 800metres last autumn, it has been a good winter. The work consisted of turf cutting the turf off, trenching out the drain lines, backfilling with sand, consolidating and finally putting the turf back on. It was a great team effort and once these areas settle down secondary drainage will be installed with a gravel bander.

Marking out the 15th approach
Gully pots going in to the 15th fairway


Turfcutting the areas

Trenching away
Checking levels




Pipe laid
Nice clay sub base in 15th green

Sand backfilled
Finished product

Gully pot installed
Marking out irrigation lines


Turf back on

Trenching across the 15th fairway

We needed some help!


382metres installed in the 15th fairway in 3 days

Marking out the 8th approach

View up the 1st fairway

1st fairway finished

Turf cut off the 8th green
Nice to know the aeration/spiking programme is working!


Typical greenkeepers!
Trench finish on the 8th green

Consolidating the sand

It's not suppose to be enjoyable


8th Approach all finished